Club History
History of Curling in Deep River
Deep River Curling Club Ltd was established as a shareholder-owned club
by Letters Patent granted in 1950. At that time AECL owned virtually all
the property in Deep River and opportunities for recreation, other than
making babies, were very limited. The curling ice was set up in a drafty
one-story U-shaped wooden building located behind the telephone exchange
(where the Huron street apartments are today). Two sheets of ice were
installed in each wing of the building, while the bottom of the "U"
housed a lounge, a bar, lockers and washrooms. The first refrigeration
plant was undersized for making ice in the fall, and a second
refrigeration unit was added in 1961. The ice area was uninsulated and
unheated for the first ten years, which made curling a sport for the
hardy. Nevertheless the ice was always busy with about 200 men using it
at night and on weekends, and with their wives using it on weekdays.
DRCSC Club Executive 1950 to 1951: Fred Gilbert, Fred Bainbridge, Tom Bailey, Ed Denke, Pat Bainbridge, Lil Greenway, Mary D'Aoust, Chris Gilbert
Between 1957 and 1963 there were two major attempts made to amalgamate
the curling and golf clubs and to build new curling facilities adjacent
to the golf clubhouse. Amalgamation was rejected by the golfers,
however, and the curlers decided to build a new clubhouse on their own.
AECL offered them a new site behind the arena in exchange for the old
site and an offer by AECL to relocate the refrigeration plant free of
charge. The new building cost $80,000 and opened in 1964. About $70,000
of its cost was raised by selling 6.5% interest bonds to be redeemed
over a 20-year period. One further attempt to amalgamate the clubs was
made in 1970. The executive of both clubs agreed that the first step
would be to convert the legal structure of both clubs from shareholder
ownership to member ownership. This was done over the next three years
but no further steps were taken towards amalgamation.
Deep River Curling, Dr David Keyes circa 1950's
The refrigeration plant has undergone many changes over the years. These
changes were made to simplify the plant, to reduce operating problems,
and to minimize costs. Major work was done in 1989 when the 39-year-old
steel pipes under the rink floor were replaced with plastic pipes.
Insulation was installed under the pipes at that time, but this has not
been successful in eliminating ice heaving that occurred with the
original installation. Further work needs to be done on the rink floor,
and will be done soon if we get a Trillium grant.
Deep River now has many other recreational facilities that compete with
curling. The curling membership is much older and much smaller than in
the good old days. Having a club with lots of senior members has some
advantages, however. The seniors are available and volunteer to tackle
most of the jobs that used to be done by hired help. This has helped to
keep membership fees at reasonable levels.
Start-up of the Squash Club
In the late 60's and early 70's, there was no squash in Deep River, yet
a number of players had experienced the game, largely in the U.K. Play
was possible at the Petawawa army base, at the modest cost of $10 per
year. So on one of these trips, while relaxing at the bar, the idea of
building in Deep River was raised once again. Two earlier attempts had
failed. However, it was agreed that a third attempt be tried, since
Wintario matching grants were available, but possibly not for much
longer. Ian Glen volunteered to manage the project, Mike Watson to chase
potential donors, and John Morralee to carry out drafting.
A key need was someone with civil/construction background, and Jerry
Lemon volunteered, while Janis Gulens organized the volunteer work
parties. John Hilborn and Peter Garvey rounded out the committee.
It was estimated that two courts could be built for under $72,000 with
volunteer labor. Our application for a Wintario grant was rejected in
early 1979, but "would be reconsidered if we applied as the Curling and
Squash Club". So it was time for action. A committee was set up
consisting of curlers Don Ross, Leo Buckley, and S. L. Beamish, and
squash players Ian Glen, John Hilborn, and Peter Garvey. The basic
concept would be that all costs would be bourn by squash players, while
the land would be provided by the Curling Club, and common operating
costs would be shared by an amalgamated club. A key aspect demonstrating
viability was the collection of un-cashed cheques, of largely $200 from
50 potential members, for a total of $12,000.
So the crucial meeting occurred on May 7 1979, when the Curling Club
members had to vote to amalgamate or not. While the Curling executive
had approved the Squash Club addition, a vote by the Curling members was
needed, and since a money by-law was involved, a 2/3 approval was
needed. Of 110 votes cast, including last minute proxies, approval
received 75, while 35 were against. A cliffhanger won by 1.7 votes.
Thereafter, the $36,000 Wintario grant was approved, and the courts
built for about $65,000 plus volunteer labor. Operation started in the
fall of 1980, and membership was 170 for each of the first four years -
a success!
Building the Squash Courts
With the Curling Club's approval in May 1979 to become the Curling and
Squash Club, and with a subsequent Wintario promise of $36,000, and
donations of $12,000, the construction started.
The plan was to join onto the south wall of the existing curling club
lounge. Two courts would be constructed rather than one. The new
facility would open up and improve the lounge, yet provide viewing to
one court. The other court would have a viewing area open to the court,
and accommodate larger crowds for championship match viewing. Beneath
these areas would be ladies and mens changing rooms with showers and
toilet facilities.
Early on, following excavation, volunteer labour seemed to consist of
shoveling and shoveling sand, at the bottom of a one story pit The basic
construction consisted of block, laid by sub-contractor on concrete
footings. Reinforcement was by tie-rods and concrete in the block
cavities. Plumbing had to be laid below the basement floor level. One
gut-wrenching accident with a bulldozer while back-filling was quickly
righted.
Flat roofing kept the construction cost reasonable, with little
subsequent maintenance over the years.
A major innovation was to apply fiberglass coating directly on the
concrete block. High quality courts were then built using ¾ inch thick
plaster walls. In Canada, the experience had been that fiberglass was
needed to stop ablation of the plaster by the ball. J.Lemon had
experienced putting the fiberglass straight on the concrete block.
Sample fiberglass was found to be immune to pounding by a 2 x4. Thus we
saved the plaster cost, and now own the biggest squash courts in Canada
by 1.5 inches. They have been almost maintenance free for 20 years. The
technique required that the blocks be laid true as possible, interstices
ground smooth, fiberglass sanded smooth etc. Lots of dusty manual
labour.
Other features were a professionally laid sprung hardwood floor. No
sealant was applied, or ever should be, based on squash-expert advice.
The only maintenance needed over 20 years was to correct lack of
edge-clearance to avoid buckling from humidity, and fine sanding once or
twice.
Lighting was at the minimum recommended, and was uprated years later. By
the fall of 1980 the courts were open, and extremely popular.
|